PlantHire

# Know what is on hire and what it is costing

PlantHire holds the hire register of each contract: the item, the supplier, the on-hire and off-hire dates, the hire rate with the supplier's charging basis, the one-off charges and the supplier's invoices. A hire still on hire after its expected off-hire date is marked as overrunning, with what each further week costs. Each hire's cost is plant cost in CommercialCVR, on its cost code, without being entered twice.

Hire

Record each hire with its supplier, cost code, on-hire date, expected off-hire date and rate per day or per week. It is on hire from today unless you give another date.

[Read workflow steps](<https://quantsurv.ai/media/products/transcripts.txt>)

On site

The plant on hire now, with any hire past its expected off-hire date listed first and what each further week costs. Open a hire to record its off-hire.

[Read workflow steps](<https://quantsurv.ai/media/products/transcripts.txt>)

Off-hire

Plant taken off hire, with the supplier’s off-hire number and the off-hire notice to send yourself. Close a hire once its last invoice is in.

[Read workflow steps](<https://quantsurv.ai/media/products/transcripts.txt>)

Cost

Each hire’s accrued cost, its rate for the days charged plus one-off charges, against the supplier’s invoices. An invoice past the off-hire date or above the accrued cost is pointed out.

[Read workflow steps](<https://quantsurv.ai/media/products/transcripts.txt>)

## Questions about PlantHire

### How is a part week charged?

As the supplier charges it. On a weekly rate you choose whether a part week is charged by the day, at the weekly rate divided by the days in the charging week, or as a full week. Take the basis from the hire agreement.

### When does a hire become cost?

From its on-hire date. CommercialCVR reads the hire rate for the days charged up to the report's period end, plus the one-off charges dated by then.

### What does PlantHire not handle yet?

Minimum hire periods, bank holidays, standing time rates and rate changes during a hire. Nothing is sent to a supplier and no invoice is paid from PlantHire.

### Does PlantHire off-hire the plant for me?

No. It records the off-hire and prepares the notice. You send the notice to the supplier and record the off-hire number they give you.

### What if the supplier invoices past the off-hire date?

The hire shows the invoice against what it accrued and points out the difference, so you can ask for a credit note. Record the credit note as a minus amount.