PrelimTracker

# Know what your prelims have cost and what they will cost

PrelimTracker holds the prelims of a contract after award: the preliminaries, the costs of running the site. Each item is fixed, a one-off sum such as mobilisation, or time-related, a weekly rate over a period such as supervision or cabins, with its budget from the tender allowance. Cost to date is read from the contract's cost ledger by cost code and from PlantHire, so nothing is entered twice. The forecast runs to the completion date held in ContractCentre.

Schedule

Add each prelims item against its cost code as fixed, with a sum, or time-related, with a weekly rate, weeks and a start date. A time-related item runs to its own end date or the contract’s completion date.

[Read workflow steps](<https://quantsurv.ai/media/products/transcripts.txt>)

Cost and forecast

Each item’s cost to date is read from its cost code in CommercialCVR and from linked PlantHire hires, never typed in. Its forecast, variance and working show as at the date you choose, with the prelims report to download.

[Read workflow steps](<https://quantsurv.ai/media/products/transcripts.txt>)

Weekly rate

What the time-related items running on a date cost for a week, beside each item’s average weekly cost to date

[Read workflow steps](<https://quantsurv.ai/media/products/transcripts.txt>)

## Questions about PrelimTracker

### Do I enter cost in PrelimTracker?

No. Cost is recorded once, in the contract's cost ledger, against a cost code: a supplier invoice in OrderBook, an approved week in TimeSheets, a hire in PlantHire or a cost entered in CommercialCVR. PrelimTracker reads it.

### What happens if two items share a cost code?

The ledger holds one figure for a cost code, so it cannot be split between two items. The first item carries the code's cost and the other is pointed out. Give each item its own cost code, or keep them as one item.

### What happens when the completion date changes?

Revise it in ContractCentre. Each item that runs to the completion date is then forecast to the new date. Nothing is entered again in PrelimTracker.

### Is the weekly rate what a prolongation claim recovers?

No. It records what the time-related items cost for a week on a date, with each item's average weekly cost to date beside it. What a claim recovers, and on what basis, is decided by your contract.